Lucan Track Build

 

 

Lucan Track Build

 

 

Location: St. Catherines Park, Lucan

 

Contractor: Euro Services

 

Designer: Kelvin Batey

 

 

 THIS PAGE WILL BE UPDATED REGULARLY, CHECK BACK SOON.

PLEASE DO NOT  VISIT THE TRACK SITE DURING CONSTRUCTION AS THERE IS NO PUBLIC ACCESS AND AS WITH ALL CONSTRUCTION SITES, IT IS DANGEROUS.

 

 

 

14th March 2014 Almost there now. Start hill and berm 2 to tar. Gate arrives in April. Fence, power and water next.

 

 

 

 

 

5th March 2014 Final shaping done (mostly) and surface going on.

 

 

 

 

 

 

 

25th February 2014 3rd and 4th straight coming along nicely.

 

 

 

 

 

 

 

19th February 2014 lots of work on jumps happening but still shaping to do, third straight got going today. Video does not convey the scale …

 

 

 

 

17th February 2014 more work on jumps, shaping and layers of stone.

 

 

 

 

 

 

 

 

14th February 2014 fourth straight coming together, some shaping still to do. Berm 2 rises from the ground.

 

 

 

 

 

 

 

 

31st January 2014 Jumps slowly appearing, weather has not been ideal!

 

 

 

 

 

 

 

 

 

23th January 2014 First Berm is almost done.

 

 

 

 

 

 

 

20th January 2014 First layer of tar going on to the monstrous first berm.

 

 

 

 

 

17th January 2014 First bike on the track for some berm testing. Berm 1 gets some more shaping for tar.

 

 

 

 

 

 

 

 

 

16th January 2014 Berm 3 gets a coat of Tarmac … big day! Start Hill gets a little higher along with some shaping.

 

 

 

 

 

 

 

 

10th January 2014 Important but unsexy stuff like drainage is complete. Berms 1 and 3 get some shape. Are they some jumps appearing?

 

 

 

 

 

 

29th November 2013 Start hill reaches 5 meters.

 

 

 

 

20th November 2013 The four straights are laid out, first and third berms started.

 

 

 

 

 

 